A modern gym required a high-capacity cooling system that could handle large open spaces, heat-generating equipment, and fluctuating occupancy while fitting within structural and construction constraints.
Instead of three large 195 kW rooftop units, the project used twelve Braemar 51 kW RTP units. This modular design improved zoning, balanced rooftop loads, simplified installation, and reduced structural concerns.
The result was a cost-effective HVAC solution with flexible cooling control, improved durability for Queensland conditions, and an estimated 18–25% reduction in energy use, all delivered within the builder’s 12–14 week construction timeline.
A modern gym environment with:
• Large open training areas
• High ceilings
• Group fitness rooms
• Office and reception spaces
• Heat generating equipment
• Fluctuating occupancy throughout the day
This required a system capable of delivering strong cooling performance while avoiding unnecessary energy use during off peak periods.
The original design placed three large 195 kW units in a single cluster. Structural engineers raised concerns about:
• Concentrated load points
• Restricted airflow
• Challenging maintenance access
The builder required a solution that could be delivered and installed within 12–14 weeks, aligning with the gym’s planned opening date.
Instead of the originally specified three large 195kW capacity units, Primo Air supplied twelve Braemar 51 kW Rooftop Package (RTP) units. This modular approach delivered several key advantages:
By distributing units across the roof, the gym can now:
• Activate cooling only in areas currently in use.
• Reduce energy consumption during low traffic periods.
• Improve comfort control in group fitness rooms, weights areas, and admin spaces.
This zoning capability is further enhanced by the ability to link multiple RTP units to a single wall controller, simplifying operation for staff.
The smaller units allowed strategic placement across the roof, resulting in:
•Even load distribution.
•Better airflow around each unit.
•Safer and easier maintenance access.
Each Braemar RTP unit includes:
• Black Fin Coil Protection for corrosion resistance.
• Weather resistant panels designed for harsh Queensland conditions.
• Redundancy uses a dual compressor configuration for continued operation during maintenance and service requirements.
• Flexible output capacity, using a DC Inverter compressor.
• Reliability, R32 refrigerant leakage sensor for safe operation.
These features ensure long term reliability in a high humidity, high UV environment.
Switching to Braemar delivered significant savings for both the contractor, builder and client:
Lower Equipment Cost
• The modular 51 kW units provided a more cost effective alternative to the originally specified large capacity systems.
Reduced Installation Costs
• Smaller units meant:
• Simplified cranage
• Faster installation
• Less structural reinforcement required
Long Term Operational Savings
• The zoning flexibility is expected to reduce annual energy consumption by an estimated 18–25%, based on typical gym usage patterns.
With the Braemar’s 12–14 week lead time, it aligned perfectly with the builder’s schedule and meeting the deadline. All units were delivered on time, allowing the mechanical contractor to complete installation without delays and ensuring the gym opened as planned.
The completed system provides:
• Reliable, high capacity cooling
• Flexible zoning for energy efficiency
• Durable equipment suited to Queensland’s climate
• A cost effective solution that exceeded the builder’s expectations
Builder: Clarke’s Design & Construct
Installer: Primo Air
Download Case Study View Product
Sport & Leisure Centres
Australia
Queensland
Rooftop Packages
Heating and Cooling
Braemar